Highway maintenance

All minor repairs identified from our safety inspections are prioritised for action depending on their severity, location and the hierarchy of the road or footway.

They might include:

  • Raised flagstones
  • Kerbs
  • Potholes
  • Highway drains/gullies
  • Road markings
  • Highway grass verges and weeds
  • Fences, guardrails, crash barriers
  • Overgrown vegetation
  • Damaged, missing or uneven manhole covers.

When you inform us of damage to a footway or carriageway, we will, wherever possible, make contact with you within 1 working day and conclude the enquiry within a maximum of 10 working days.

Other problems

Street works, roadworks, skips, scaffolds, hoardings, advertising boards and building materials that block the pavement can be considered to be causing an obstruction to pedestrians.

Carriage and Footway planned maintenance

Carriageways Surface Dressing Sites – January 2018 Update

Carriageway Surface Dressing (CSD) is a preventative maintenance treatment that was applied to a number of carriageways (listed below) in September 2016.

This process has been used throughout the borough (and the UK) for many years with great success. The CSD provides a waterproof coating to the carriageway that prevents the ingress of water and at the same time it provides an improved carriageway.

During September 2016 a total of 12 sites across the borough were treated with a CSD preventative maintenance treatment. In November 2016 it was noticed that a number of these sites had started to lose the stone chippings and were starting to show early signs of failure.

Failures were monitored during the 2016/17 winter period and it was agreed with our contractor that some of the affected areas would be treated again with CSD. However, on some high stress sections a secondary preventative maintenance process known as Micro-asphalt would be used. Our contractor will carry these works out at no cost to the council.

In August 2017 the CSD remedials were completed by our contractor and the Micro-asphalt sections commenced in October 2017. Unfortunately, due to reduced temperatures we were unable to complete all the Micro-asphalt remedial works at that time. Therefore they have been scheduled to be completed in spring 2018 once ambient temperatures increase.

During November/December 2017 the councils engineers noted that the remedial works were showing signs of premature failing for a second time. Our contractor was made aware of these additional failures and are completing their surfacing treatments work as detailed below:

Preventative Maintenance Sites

Site information - All dates are weather dependant
SiteDate of planned works
Hall Lane, Aspull - (Mayfair Dr - Pennington Green Ln) Carriageway resurfaced February 2018
A49 Wigan Road, Bryn - (Soughers Lane - Downall Green Road)  Micro asphalt treatment planned for September 2018 (delayed due to utility works)
A58 Lily Lane, Platt Bridge - (Canal Bridge - Wigan Street) Micro asphalt laid in April 2018
A49 Central Park Way, Wigan - (Penson Street - Douglas Bridge)  Micro asphalt treatment laid on 29th April 2018
Nel Pan Lane, Leigh - (O/S No. 285 - Barrie St)  Micro asphalt treatment laid in April 2018
A573 Warrington Road, Abram - (Willow st - Kirkham St)  Micro asphalt treatment laid in May 2018
A573 Warrington Road, Abram - (Abram Village Club - Park Ln)  Micro asphalt treatment laid in May 2018
A577 Manchester Road, Ince - (Moat House Street - Makerfield Way)  Micro asphalt treatment laid in May 2018
A577 Manchester Road, Ince - (Makerfield Way - O/S No.206)  Micro asphalt treatment laid in May 2018

Relevant documents

A-Z

Rate the information on this page

green smiley (good) orange smiley (average) red smiley (poor)

© Wigan Council