Committee Report: Capital Project Appraisal Cycle for 2007/08 Capital Programme

Report to:

Cabinet

Date:

16th November 2006

Subject:

Capital Project Appraisal Cycle for 2007/08 Capital Programme

Report of:

Director of Finance & IT and Assistant Chief Executive

Contact officer:

Andrew Taylor – 01942 827243

Purpose / summary:

To update members on the capital appraisal cycle and recommend projects for inclusion in the capital programme 2007/08 onwards

Alternative options considered and reason for selecting the one recommended:

Not to approve projects would delay important investment in our services.

Recommendation / decision:

To accept into the capital programme those projects listed in Table 1.

To commission further feasibility / funding investigation on those projects in Table 2.

To accept the reserve list of projects in Table 3

Cabinet’s views are requested with regards to projects set out in Table 4.

Implications:

 

Financial:

Capital Expenditure plans as set out in the report. Each project has been separately appraised and revenue effects are within current budgeted levels.

Staffing:

Set out in individual project appraisals

Policy:

Pursuance of all of the Council’s strategic objectives

Equal Opportunities - Has a Diversity Impact Assessment been conducted?

 

Wards affected:

All

Special Interest Members – Which have been consulted

 

Tracking/Process:

 

Consultation

Ward Members

Partners

 

Capital Strategy Management Group

SMT 27th October 2006

-

-

Panel

Overview & Scrutiny

Cabinet

Council

-

-

6th November 2006

-

There are no Background Papers to this Report within the meaning of Section 100D of the Local Government Act 1972.

Proper Officer

David Smith

Date

6th November 2006

Background

Further to the Council’s Capital Strategy adopted by Council on 7th September 2005 the 2007/08 capital project appraisal process has been carried out. Chief Officers have prepared appraisals for projects which they would like to see come to fruition and be included in future capital programmes.

The contextual setting of the decisions members are asked to make from this report is that in the medium term the Capital Programme has a £2.0 million structural deficit in funding. This clearly reduces the scope for including Capital Projects which do not bring with them sufficient resource cover for their completion. The deficit has been arrived at after taking the following assumptions into account on Capital Receipts.

 

2007/08 (£000’s)

2008/09 (£000’s)

General Receipts

2,500

2,500

Right to Buy Receipts (Usable Proportion)

2,650

2,650

Earmarked / Ring fenced

16,451

1,800

Total

21,601

6,950

Capital Project Management

The scale of investment in Capital Projects is large and a few of the proposals in this report are in the region of £20million. Clearly such projects will be the subject of further detailed reports to members as they progress from inception, through procurement and on to delivery. It is critical that sufficient arrangements are made to ensure adequate management of these projects to ensure delivery on time and on budget.

Prioritisation of Projects

It is a key test of prospective capital projects that they are in line with the achievement of the Council’s strategic objectives. All of the project appraisals which were received in this round of appraisals demonstrated that projects would indeed contribute towards Council objectives. The Capital Strategy Management Group has assessed the appraisals against corporate priorities, and a recommended order of prioritisation against the criteria set out within the Capital Strategy, has been compiled. It has previously been indicated that given the overall position of the capital programme the most likely new programmes and projects will either be government supported or invest to save.

A summary of the projects and recommendations in the following categories is as follows:-

Table 1. Recommend for inclusion in 2007/08 programme onwards (all projects fully resourced)

Project

Project Capital Costs (£000s)

Adult Services

Integrated Children’s Systems (delivered via Adult Services Dept)

334.0

Mental Health SCE(R) 2005/06 (uncommitted Resources C/F)

185.5

Mental Health SCE(R) 2006/07 (uncommitted Resources C/F)

144.0

Preventative Technology

511.0

Replacement Information Systems

611.0

Children’s and Young Peoples Services

BSF Pathfinder – New Secondary School

18,500.0

Single Site Lamberhead J & I

1,500.0

EBSD Review

12,793.3

Landgate School – Additional Accommodation

350.0

Marsh Green School

1,025.0

Oakfield New School

5,200.0

Sure Start Phase 2

4,744.4

Housing General Fund

Private Sector Housing – Adaptations (Grant funding)

780.0

Private Sector Housing – Renewal

4,400.0

Bickershaw Travellers Site (A grant of 75% is potentially available from government, this must be confirmed. Balance of funding from existing resources)

287.0

Ince Central Contaminated Land Remediation Phase 3

(Funding support now agreed by DEFRA)

1,002.0

Legal and Property Services

Trencherfield Mill Steam Generating Boiler Replacement

(Prudential Borrowing for the Project Approved By Cabinet 06/02/06

Decision on other boiler delayed under scheme funding on retained area)

 

177.8

Wigan Markets Improvements Plan 2006/07 Phase 1

Project approved by Cabinet 15/12/05

466.3

Wigan Markets Improvements Plan 2006/07 Phase 2

Further Works made possible by larger than expected capital receipt.

277.6

Planning And Regeneration

Bickershaw Colliery Reclamation

19,300.0

WALH

Completion of ALMO Improvement Programme 2007/09

47,100.0

Environmental Services

A573 / A58 Platt Bridge

200.0

Birket Bank

520.0

EDZ Dropped Crossing And Tactile Paving

110.0

EDZ Parsons Meadow

250.0

Hindley Town Centre

475.0

Leigh Bus Station

150.0

Leigh To Bolton Phase 4

110.0

Newton Road / Kenyon Lane

250.0

Ormskirk Road / Fleet Street

300.0

Orrell Post

250.0

Robin Park / Scot Lane

150.0

Shakerley Area Traffic Calming

125.0

St Paul’s Ave

140.0

Standish Town Centre

215.0

Wallgate Pedestrian Improvements

200.0

Whelley Loop Off-Road Cycleway

370.0

Wigan To Ashton A49

100.0

Cultural Services

Mesnes Park (Commitment to meet shortfall of £500k already approved by Cabinet 24th August 2006)

 

2,316.0

Pennington Park Visitors Centre (Funded from British Coal compensation)

 

230.0

Table 2. Recommended for further feasibility work / delay until external approval for funding is received.

Project

Project Capital Costs (£000s)

Comment

Amount Sought from Council Resources (£000s)

Goose Green to Westwood Park Link Road

19,769.0

Dependencies around Chinamex proposal. This project forms part of Access Wigan (A5225) Highway proposal

0.0

Ince Central Contaminated Land Remediation Phase 4 -9

4,736.0

Project will attract support from Defra – later phases presently not approved (Balance from HRA Capital Programme)

318.0

Libraries

2,000.0

Proposed match funding of lottery bid.

1,000.0

The Grange Community Centre at Hope

1,594.7

Further discussions taking place 1st November 2006.

165.0

Grass Pitches – Hesketh Meadows

160.0

£80k funding included in existing Capital Programme but can only be drawn down to match grant bid.

80.0

Grass Pitches Ph2

400.0

50% Football Foundation grant other external funding to be investigated

200.0

2006/07 Project :- Trencherfield Mill Performance Venue

7,741.0

Further options appraisal being conducted.

 

2006/07 Project :- Learning & Physical Disability Accommodation Support Unit

700.0

Project scope being reviewed with the intention of re-submitting a revised bid next year

 

2006/07 Project :- History Shop improvements to Access

400.0

Was £1m but bid now reduced to £400k and expected to be submitted to HLF prior to end of year there is a six to nine month turnaround at the HLF

 

Table 3. Recommended as reserve projects to be brought forward if sufficient funding should come available.

Project

Project Capital Costs (£000s)

Comment

Haigh Roads Improvements

750.0

Currently there is no funding for the scheme

Heritage Store

500.0

Currently there is no funding for the scheme

Parks Strategy

2,500.0

Currently there is no funding for the scheme

2006/07 Reserve Projects :-

Tyldesley Library

3,812.5

Funding gap of £3,562K

Play Area Renewal

2,750.0

Funding gap of £2,337K

Turnpike Centre

750.0

Funding gap of £500K

The following items are presented separately as these are projects which rely upon the successful achievement of capital receipts targets each year in order to finance their expenditure. The Right to Buy capital receipts generated from the sale of Council Houses effectively support the £2.5m / annum disabled persons' aids and adaptations programme. However it is felt that Right to Buy receipts over the next few years are likely to decline. Likewise the Land Disposal Programme, which can often create difficult decisions for the Council, provides resources which enable the Capitalised Repairs programme to be delivered. Therefore, a decision not to sell a high value piece of land should be taken in the context that it would impact directly on the Council's Capital Programme. In the light of changing circumstances and competing demands for capital resources, Cabinet’s view is sought on the continuing support of these programmes.

Table 4. Decision requested from Cabinet. (NB All these projects are in line with Council Objectives)

Project

Annual Capital Costs

£000s

Comment

Disabled Persons Adaptations (per annum)

2,500.0

 

This programme has traditionally been supported by Right to Buy capital receipts. The current programme contains provision for the years, 2007/08 to 2009/10. Against the Council’s agreed capital strategy prioritisation criteria this project is effectively dependent upon a decision from members as to its future. In making the decision Members’ attention is drawn to the overall deficit on the capital programme.

It is recommended that beyond 2007/08 this provision is reviewed in the light of the circumstances which the Council is likely to face at the time. Therefore as part of the overall capital appraisal process the continuation of the programme at current levels will be assessed against competing demands.

Capitalised repairs (per annum)

2,300.0

This annual programme has no supporting resource. The current programme contains provision for the years, 2007/08 and 2009/10. Against the Council’s agreed capital strategy prioritisation criteria this project is effectively dependent upon a decision from members as to its future. In making the decision Members’ attention is drawn to the overall deficit on the capital programme.

It is recommended that beyond 2007/08 this provision is reviewed in the light of the circumstances which the Council will face at the time. Therefore the continuation of the programme at current levels will be assessed against competing demands.

Private Sector Housing – adaptations –Non grant funded proportion i.e. 40%

520.0

This proportion of Private Sector DFG has been traditionally met from General Capital resources (Mainly Capital Receipts). The current programme contains provision for the years, 2007/08 to 2009/10. It may be possible to fund all or part of this complementary funding from mainstream PSHR grant which would of course reduce overall spend but also the deficit on the capital programme.

It is recommended that beyond 2007/08 this provision is reviewed in the light of the circumstances which the Council will face at the time. Therefore the continuation of this contribution to this programme at current levels will be assessed against competing demands.

Conclusions and Recommendations.

The Council’s Capital Strategy requires that potential projects and programmes are appraised alongside one another to ensure that members may consider the choices which are available regarding the make up of the capital programme. The Capital Programme’s medium term prospects are that of a £2.0 million structural deficit and this means that projects tend not to be included in the programme unless they bring with them sufficient resource cover to complete them.

The exceptions to that rule are those projects where an emergency situation has arisen and the 2 major annual programmes – aids and adaptations for disabled persons (both for Public & Private Sector Housing) and the programme of capitalised repairs.

Cabinet is asked to consider the proposals set out in tables 1 to 4 and :-


Return to Agenda

ABCDEFGHIJKLMNOPQRSTUVWXYZAll