| On-going |
Primary Capital Pilot (Leigh) |
Rebuilding of Leigh Central and Sacred Heart Catholic Primary Schools. Commencement due July 2008. Completion due September 2009. |
| On-going |
Pathfinder High School (4023) |
Relocation of new Abraham Guest High School. Commencement due June 2008. Completion due December 2009. |
| On-going |
Oakfield High School (7015) |
Relocation of special school. Completion due September 2008. |
| On-going |
New schools - new name pending |
Following a successful Targeted Capital Bid, Wigan will be building one new EBSD secondary school, 2 resourced primary PRUs (one on each side of the borough), and a KS3/4 PRU in each of the 3 collaborative areas |
| On-going |
Marsh Green Primary (2009) |
Reduce school to 1 form of entry |
| On-going |
Hindley Green C.P School (2032) |
Single site school |
| October 2007 |
Golborne County Primary School (2037) |
New school building - reduction in places and complete rebuild |
| May 2006 |
Westfield School (3437) |
New 2 form entry school - amalgamation of former Scot Lane and Pemberton Primary Schools |
| October 2006 |
Lamberhead Green Community Primary School (2064) |
Remove temporary buildings and reduce to 2 form of entry |
| October 2006 |
Hindley Community High School (4026) |
Provision of a resourced base for pupils with special needs. |
| November 2006 |
Platt Bridge Community First (3436) |
New 1.5 form of entry school with nursery and assessment unit - amalgamation of former Low Hall and St Nathaniels CE Primary Schools. |
| September 2006 |
Montrose School (7016) |
Remodelling |
| September 2006 |
Green Hall Primary School (7014) |
Remodelling |
| September 2006 |
Brookfield High (7015) |
Remodelling |
| October 2005 |
Hindley J&I School (2031) (.pdf, 531KB) |
New school building - complete rebuild incorporating facilities for special needs pupils. |
| August 2005 |
Fred Longworth High School (4025) |
New block |
| April 2005 |
Woodfield J&I School (2007) |
New school building - complete rebuild |