Having considered a report that concerns;
- A scheme entailing the construction of two new modular Pupil Support Centres on Beech Hill and Newton Westpark Primary Schools
- The approval of the competitive tender from Wernick Buildings Limited in the sum of £691,203 within the out-turn figure of £816,628 and;
- The granting of budget release from the LEA`s Targeted Capital funding in the sum of £816,628
I made the following Executive Decision in relation to two new modular Pupil Support Centres on Beech Hill and Newton Westpark Primary Schools;
To approve the establishment of two new modular Pupil Support Centres on Beech Hill and Newton Westpark Primary Schools;
- To approve the competitive tender of £691,203 within the out-turn figure of £816,628 and;
- Grant budget release from the LEA`s Targeted Capital funding in the sum of £816,628
Since this is an Executive Key Decision, the decision will come into force, and may then be implemented, on the expiry of five working days after the publication of the decision i.e. 30/5/2008, unless the Overview and Scrutiny Committee objects to it and calls it in.
Date of decision: 9 May 2008
Date of publication: 21 May 2008
Name: Councillor P R C Smith - Executive Leader