Description:

 

Has the local planning authority met the milestones which the current Local Development Scheme (LDS) sets out?

 

Comments on our performance in 2006-07

 

The Core strategy and Allocations plan were met in October 2006.

The Statement of Community Involvement was met in July 2006, one month late as the SCI could not be adopted until a decision had been made by Council which did not meet until July.  The LDS milestone had been changed to June late in the process on the recommendation of Government Office North West.  

how to use this performance briefingBV106BV111BV109aBV109bBV109cBV200c Annual monitoring reportBV 204 Appeals against refused planningBV 205 Quality of ServiceCor Plan: Number of new businessesCor Plan: Private sector investmentRegeneration programmes spent to profileCor Plan:Commercial property leased/soldVisit INPHASE